Typical Manifold STP/IST's

STP INSTALL OUTLINE, TOP VIEW DRAWING

Notes: 14" on center offset shown is recommended minimum with installation of STP/IST #1 prior to that of STP/IST #2. A smaller offset or other changes to the STP/IST installation may require a larger sump riser diameter, alterations or additions to the piping shown, turning of the STP/IST's other than shown to accommodate piping, or disassembly of the junction box from the STP/IST to allow for turning of assembly into the tank. Minimum offset of STP/IST's is 12".

*STP/IST must be used with either the STP-SC or IST-VFC (IST 2 HP only) controllers for proper mechanical line leak detection, see TB013 for details.